CONSTRUCTION OF OFFSHORE WORKS OF CANDARLI CONTAINER PORT
​
LOCATION: IZMIR / TURKEY
CLIENT: LİMAK&KOLİN JV
COMPLETION DATE: 28/02/2014
PROJECT DESCRIPTION:
Driving 70''inch steel pipe piles
Construction of complementary works to form breakwater structure
Splicing, manipulating and driving 112 tons of 1787 mm diameter t:25mm steel pipe piles
Formwork,reinforcement,precast and cast insitu concrete works.
Temporary loading quay and temproary service jetty constructions
​
​
​
​