CONSTRUCTION AND INSTALLATION OF GOLCUK SUBMARINE PIER AND BUILDINGS

LOCATION: IZMIT / TURKEY

CLIENT: Ministry of National Defence,

Construction and Real Estate Department,

Infrastucture Department

COMPLETAION DATE: 07/02/2007

PROJECT DESCRIPTION:

25 m in lenght and 5 m in width transportation jetty 

25 m in lenght and 8 m in width berthing jetty 

3728 m Dia:32'' pile driving 

6832 m3 excavation 

780 m3 fill

1981 m3 concrete 

349 ton RC rebar 

65 ea provision and installation of rubber fender 

​